Skip to main content
Loading…
This section is included in your selections.

A. Before building permits are issued, the builder shall deposit with the city a bond sufficient to guarantee completion as determined by the city engineer, and in no case shall the bond be less than two hundred fifty dollars per valve, sixteen dollars per lineal foot of pipe and one thousand three hundred dollars per hydrant.

B. Before release of the bond, all hydrants in the subdivision shall be in good working condition, caps in place, auxiliary valve and street box installed to finish grade. The sidewalk flange shall be level with the sidewalk or finished grade. The bond shall not be released until the city engineer has accepted the facilities in writing. (Ord. 8/27/2002B (part))